But at each step, you discover another step you didn't originally anticipate

That is the core of your problem. Since it's happening repeatedly, you should stop assuming that you know the distance to completion and assign a probability distribution to the number of step (or time) needed to get the project done, likely with a long right tail.

If you constantly encounter the unexpected, you should acknowledge that your expectations are faulty and start to expect the unexpected.